Date the item is expected to be delivered based on the vendor lead time. For Buy to Order items, if the number of days between the Required Date and the Order By Date is equal to the vendor lead time the Expected PO Date will be equal to the Required Date. If the number of days between the Required Date and the Order By Date is less than the vendor lead time then the Expected PO Date will be equal to the Order By Date + the vendor lead time.
For Buy Stock Items the due date calculation is today’s date + the Item Vendor Lead time for the Primary Vendor of that item.
|